Arbitration Clause Does Not Bar Contempt Jurisdiction; Bombay HC Signals Tough Contempt Action Against Developer for Bounced Cheques and Redevelopment Delay

Arbitration Clause Does Not Bar Contempt Jurisdiction; Bombay HC Signals Tough Contempt Action Against Developer for Bounced Cheques and Redevelopment Delay

Tilak Nagar Sri Gurudutta Cooperative Housing Society Limited vs Mishal Construction Pvt Ltd [Decided on November 21, 2026]

Justice Amit Borkar

The Bombay High Court has ruled that the existence of contractual remedies, termination rights, execution proceedings, or arbitration clauses does not oust the Court’s contempt jurisdiction where an undertaking given to the Court is alleged to have been violated. Accordingly, the Court Dishonour of cheques that were issued pursuant to such undertakings, coupled with allegations of continuing non-cooperation in performing redevelopment obligations, can constitute sufficient material for issuance of a show-cause notice in contempt proceedings.

The Bombay High Court held that the settlement terms executed between Mishal Construction Pvt Ltd. and Tilak Nagar Sri Gurudutta Cooperative Housing Society Limited were not merely contractual arrangements, as the parties had expressly recorded them as undertakings to the Court and the earlier Section 9 proceedings were disposed of on that basis.

Also read PMLA Adjudicating Authority Must Include Judicial Member When Confirming ED Attachments: Supreme Court

Since two cheques of Rs. 51 lakhs and Rs. 77 lakhs issued under the settlement were dishonoured for ‘Funds Insufficient’, the High Court noted that the Consent Terms themselves declared dishonour of even one cheque as a breach, creating a prima facie case requiring an explanation from the developer. Rejecting the developer’s preliminary defence, the Court observed that the existence of arbitration remedies or contractual consequences does not extinguish the Court’s power to examine a wilful breach of undertakings given to it.

The High Court found sufficient material to examine allegations that the developer failed to cooperate in securing approvals from MHADA and MahaRERA and in progressing the balance redevelopment work, despite express obligations contained in the settlement. As the Consent Terms specifically referred to undertakings by both the company and its directors, the Court issued notice not only to the developer company but also to its directors, requiring them to explain their alleged role in the breaches.

Also read ‘One Government Drags Its Feet, Another Acts In Haste’: SC Criticises Shifting Approach To Criminal Cases With Change In Government

Briefly, the dispute arose from the redevelopment of the property belonging to Tilak Nagar Sri Gurudutta Cooperative Housing Society Limited vs Mishal Construction Pvt Ltd, where the Society had appointed Mishal Construction Pvt Ltd. as the developer under a Development Agreement dated 20 July 2010 and a Supplementary Agreement dated 10 November 2014. The developer was required to complete redevelopment and provide permanent alternate accommodation to the existing members.

However, the project remained incomplete for several years, and the Society alleged that transit rent payments had stopped from October 2018. Consequently, the Society terminated the Development Agreement and Power of Attorney in September 2023 and initiated proceedings under Section 9 of the Arbitration and Conciliation Act, 1996.

Also read UK Court Grants Bail to Indian Criminal Lawyer Vijay Aggarwal in Sexual Assault Case

During the pendency of those proceedings, the parties entered into Consent Terms dated 10 October 2024, which were accepted by the Bombay High Court on 17 October 2024. The settlement contemplated completion of the redevelopment project, payment of outstanding dues, cooperation between stakeholders, and issuance of two cheques by the developer amounting to Rs. 51 lakhs and Rs. 77 lakhs. The Consent Terms expressly stated that the obligations undertaken by the parties would operate as undertakings given to the Court.

The Society subsequently alleged that both cheques were dishonoured for ‘Funds Insufficient’ and that the developer failed to cooperate in obtaining statutory permissions and progressing the redevelopment work. On this basis, the Society filed the present contempt petition.

Also read Anand Mohan’s Premature Release Quashed: Supreme Court Strikes Down Bihar’s 2023 Remission Policy Amendment

A Single Judge Bench of Justice Amit Borkar observed that the Consent Terms were not merely a private contractual arrangement between the parties. The Court noted that Clause 4 specifically recorded that the obligations contained therein were undertakings given to the Court, while Clauses 7, 38 and 46 further reinforced this position. Therefore, the developer’s argument that the dispute was purely contractual and could only be resolved through arbitration was not acceptable at this preliminary stage.

The Court reiterated the settled principle that while every contractual breach does not amount to contempt, a wilful breach of an undertaking given to the Court can be examined under contempt jurisdiction. The existence of execution remedies or arbitration clauses does not automatically bar contempt proceedings where a Court undertaking is alleged to have been violated.

Also read “AI Does Not Understand File as Life”: Justice Anand Pathak on Human Sensitivity and the Limits of Algorithmic Justice

With regard to the dishonoured cheques, the Court observed that Clause 13 of the Consent Terms expressly provided that dishonour of even one cheque would constitute a breach of the Consent Terms. It was undisputed that both cheques were returned unpaid due to insufficient funds. Although the developer contended that the conditions precedent for deposit of the Rs. 51 lakhs cheque had not been fulfilled, the Court held that such defences required examination after the respondents filed their explanation.

The Court particularly noted that the Rs. 77 lakh cheque represented outstanding transit rent and was required to be honoured within the stipulated period. The respondents failed to demonstrate that the amount had been paid within the agreed timeline. This allegation, according to the Court, warranted a response from the developer.

Also read Delhi High Court Seeks Centre’s Response to Saurav Das’ Plea Against Travel Restriction; Centre Informs LOC Issued

On the issue of redevelopment progress, the Court found that correspondence exchanged between September and November 2025 disclosed serious disputes regarding cooperation, permissions, expenditure, and project completion. While the respondents had raised concerns regarding the Project Bank Account and expenditure details, their reply did not adequately explain the steps taken by them before MHADA and MahaRERA to obtain necessary permissions and move the project forward. These allegations, therefore, also merited examination.

The Court further clarified that contempt proceedings would not cover alleged breaches of deadlines that had expired in October or November 2024. However, allegations of continuing non-cooperation under Clause 46 were within limitation and could be examined because the obligation to cooperate was of a continuing nature.

The Court also held that the Directors of the developer company could be called upon to explain their role since the Consent Terms specifically referred to undertakings by both the company and its Directors. Nevertheless, no final finding regarding their personal liability was recorded at this stage.

Appearances

Mr. Kalpesh Joshi with Mr. Rushikesh Kekane and Mr. Amar Parab i/by Kalpesh Joshi Associates for the Petitioner.

Mr. Rohan Sawant with Mr. Chirag Sarawagi and Mr. Shubham Shah i/by Mr. Tushar Goradia for the Respondent.

Mr. Suresh Sabrad with Ms. Jessy Payne and Ms. Neha Parte i/by Payne & Associate for the Applicant in IAL/ 35499/2026.