Bombay High Court Upholds Arbitral Rejection of Contractor’s Claims; Holds Voluntary No-Claim Certificate Bars Further Claims

Bombay High Court Upholds Arbitral Rejection of Contractor’s Claims; Holds Voluntary No-Claim Certificate Bars Further Claims

Vishal Associates vs Hindustan Construction Company [Decided on November 20, 2026]

Right to Privacy State Surveillance

The Bombay High Court has affirmed the arbitral finding that the contractor had voluntarily executed a Work Completion and No-Claim Certificate acknowledging receipt of full and final payment and waiving all future claims arising from the contract. The Court noted that the contractor never alleged coercion while signing the certificate, in its demand notice, statement of claim, or reply to the counterclaim. The allegation surfaced only after a substantial delay, making it an afterthought unsupported by contemporaneous evidence.

The High Court held that a party seeking to avoid a no-claim or discharge certificate must establish coercion, duress, fraud, or undue influence through cogent evidence. Bald assertions without corroboration are insufficient in law. Relying on established Supreme Court jurisprudence, the Court held that after concluding that the No-Claim Certificate was voluntarily executed, the Arbitrator was justified in rejecting the claims without undertaking a merits examination of the remaining issues.

Also read Regularisation Erases ‘Birthmark’ of Initial Appointment; Supreme Court Strikes Down UP’s Pension Validation Acts

Briefly, the dispute arose out of a subcontract awarded by Hindustan Construction Company Limited to Vishal Associates for execution of works on the NH-34 project in West Bengal and Jharkhand. Initially, the Letter of Intent contemplated work worth about Rs. 10.99 crores, but the subsequent Work Order reduced the contract value to Rs. 5.72 crores and shortened the completion period. During execution, the contractor raised several running bills, all of which were paid by the employer. Owing to issues including a ban on stone mining in Jharkhand and delays in project execution, the parties eventually conducted a joint measurement of the completed work and moved towards closure of the contract.

On 25 July 2011, Vishal Associates executed a Work Completion and No-Claim Certificate stating that it had no outstanding claims against Hindustan Construction Company Limited. Subsequently, final bills were prepared, an amount of Rs. 34 lakh was paid as full and final settlement, and the performance bank guarantee was also released. Nearly ten months later, the contractor issued a demand notice seeking damages and compensation, alleging that the No-Claim Certificate had been obtained under coercion and that it had suffered losses due to the short closure of the contract. Arbitration followed, but the Sole Arbitrator rejected the contractor’s claims and imposed costs. The contractor then challenged the arbitral award.

Also read Supreme Court Allows Lighting Of Karthigai Deepam At Thirupparankundram Hill On November 24; Imposes Strict Restrictions

A Single Judge Bench of Justice Aarti Sathe observed that the central issue was whether the No-Claim Certificate had been voluntarily executed or had been obtained through coercion or economic duress. The Court noted that the Sole Arbitrator had examined both documentary and oral evidence and found that the contractor had expressly admitted receiving full payment for all work executed. The Court found no reason to interfere with that factual finding.

The Court emphasized that the contractor never alleged coercion at the time of signing the No-Claim Certificate, nor in its initial demand notice, statement of claim, or reply to the counterclaim. The allegation surfaced only much later, after the full and final settlement had already been accepted and acted upon by both parties. This delay significantly weakened the contractor’s case and supported the Arbitrator’s conclusion that the plea of coercion was merely an afterthought.

Also read Delhi HC Seeks Response On Plea by Youtuber Harsh Beniwal’s Mother To Cancel Ajaz Khan’s Anticipatory Bail

The Court further observed that mere assertions of coercion are insufficient in law. A party challenging a settlement must produce convincing evidence showing how pressure, duress, fraud, or undue influence was exercised. In the present case, the contractor failed to produce any corroborative material. The Arbitrator was therefore justified in rejecting the allegation and treating the settlement as voluntary and binding.

The High Court also held that once a valid No-Claim Certificate and full and final settlement are proved, an arbitral tribunal may refuse to examine the merits of the underlying claims. The Arbitrator had first decided the issue of coercion and, having found that the settlement was voluntary, rightly declined to examine the remaining claims on merits.

The Court reiterated the settled principle that under Section 34, courts do not sit in appeal over arbitral awards. Re-appreciation of evidence is impermissible unless the award suffers from patent illegality or perversity going to the root of the matter. Since the Arbitrator’s conclusions were based on evidence and represented a plausible view, judicial interference was unwarranted.

Appearances

Mr. Mutahhar Khan a/w. Ms. Nikita Bordepatil and Ms. Tithi Raut i/b FF and Associates, for Applicant/Petitioner.

Mr. Ashish Kamat Senior Advocate a/w. Mr. Lalit Munshi a/w. Ms. Sailee Dixit and Mr. Anuj V.R. i/b. Samvad Partners, for the Respondent.