The Bombay High Court has held that although an unsuccessful party in arbitration may maintain a post-award petition under Section 9 of the Arbitration and Conciliation Act, 1996, such relief can be granted only in rare and compelling cases satisfying a higher threshold than an ordinary interim application. Where the arbitral award rejects the applicant’s substantive claim, directs return of the bank guarantee, and there exists a prior consent arrangement fixing the outer limit for continuation of that bank guarantee, the Court will not direct continuation of the security merely because a Section 34 challenge is pending, even if the opposite party is in liquidation and the challenge raises arguable issues.
Applying this principle, the Court held that ONGC had failed to establish exceptional and compelling circumstances justifying post-award interim protection under Section 9, and accordingly dismissed the petition seeking continuation, renewal, extension or substitution of the bank guarantee, while keeping all questions in the pending Section 34 and Section 36 proceedings expressly open.
A Single Judge Bench of Justice Amit Borkar observed that after an arbitral award has been rendered, a petition under Section 9 stands on a different footing, and the principles applicable to post-award relief require a higher threshold to be met. Thus, the Bench held that an unsuccessful party is not barred from seeking relief under Section 9, but such relief cannot be granted in a routine manner. Apart from a prima facie case, balance of convenience, and irreparable injury, the applicant must show exceptional circumstances such that refusal of interim protection would result in a situation which cannot later be corrected even if the challenge succeeds.
The Bench noted that ONGC had raised arguable grounds in its Section 34 challenge, including contentions relating to Clause 6.3.2, the Tribunal’s approach to proof of actual loss, and the findings on delay and categories of loss. However, the Bench held that these were matters for examination in the Section 34 proceedings and that an arguable challenge by itself was insufficient for grant of post-award interim relief under Section 9. The Bench was thus unable to conclude that ONGC had shown such an exceptionally strong prima facie case that the award could virtually be disregarded for the purpose of interim protection.
A significant factor weighed against ONGC was the existence of the Consent Terms governing continuation of the bank guarantee, which ONGC had not adequately disclosed in the present petition. The Bench observed that these Consent Terms directly concerned the duration of the bank guarantee after the award and that fairness required disclosure of such an arrangement while seeking discretionary relief. The omission was held to be material, as ONGC was effectively seeking enlargement of its rights beyond the period consciously agreed by the parties, rather than mere preservation of an existing arrangement.
The Bench further observed that the plea of urgency was weakened by ONGC’s conduct. Although ONGC was aware from the outset of the issue concerning continuation of the bank guarantee and had already sought such relief in its Section 36(3) application, it filed the present Section 9 petition only on 15 May 2026 and served it on 1 June 2026, shortly before expiry of the guarantee on 15 June 2026.
The Bench also held that although Swiber’s liquidation and ONGC’s apprehension regarding recovery were relevant factors, the bank guarantee could not be treated as a general security for all claims of ONGC against Swiber. It was furnished specifically in connection with liquidated damages under Clauses 6.3.2 and 6.3.4, and liquidation by itself was insufficient to elevate the case to the category of a rare and compelling case contemplated in Home Care Retail Marts (P) Ltd. v. Haresh N. Sanghavi [2026 SCC OnLine SC 670].
Also Read Gary Born Brings Long-Standing WilmerHale Arbitration Team to King & Spalding
Briefly, ONGC and Swiber entered into a contract dated 3 July 2010 valued at USD 148,200,000 for offshore works in the Bombay High area, as per which, Swiber was liable for liquidated damages for delay, capped at 10% of the contract value, and it was required to furnish a bank guarantee for that amount. The completion period was extended several times, each time with ONGC expressly reserving its right to recover liquidated damages. The project was ultimately completed on 24 May 2012, and a completion certificate was issued on 18 February 2013. A bank guarantee for USD 14,820,000 was furnished and later continued through DBS Bank, with validity extended up to 15 June 2026.
Disputes were referred to arbitration, and by the arbitral award received by ONGC on 9 October 2025, the Tribunal held that ONGC was not entitled to recover liquidated damages, directed return of the bank guarantee, and after adjustment of claims and counterclaims, directed ONGC to pay Swiber a net amount of USD 4,113,200 with interest at 5% per annum from the date of the award till payment. ONGC thereafter filed a petition under Section 34 and an application under Section 36(3) of the Arbitration and Conciliation Act, 1996. Since the bank guarantee was due to expire on 15 June 2026 and the challenge proceedings were still pending, ONGC filed the present petition under Section 9 seeking continuation and extension of the bank guarantee.
Swiber opposed the petition, inter alia, on the basis that under Consent Terms dated 5 September 2016, the bank guarantee was agreed to remain alive only for 120 days after issuance of the arbitral award, which period expired on 28 January 2026. It was also contended that ONGC had not disclosed these Consent Terms in the present Section 9 petition, although it had relied on them in its Section 36(3) application, and that the present arbitration being an international commercial arbitration, the scope of challenge under Section 34 remained limited.
Case Relied On:
Home Care Retail Marts (P) Ltd. v. Haresh N. Sanghavi – 2026 SCC OnLine SC 670
Case Distinguished:
ONGC v. Larsen & Toubro, Ltd. – 2026 SCC OnLine Bom 2861
Appearances
For Petitioner: Zubin Behramkamdin, Senior Advocate with Shreya Gupta, Abhijeet Sadikale, Sanjana Kattoor i/b Shardul Amarchand Mangaldas & Co.
For Respondent: Venkatesh Dhond, Senior Advocate with Vinodini Srinivasan, Ganesh Chandru, Siddhart Agrawal, Dharmesh S Jain, Shashwat Dhyani, & Arpita Tiwari i/b Anil T. Agarwal
![]()
Oil and Natural Gas Corporation vs Swiber Offshore Construction PTE Limited

